Registration Open for Funded Project Areas



Updates

Late August Update for Quilcene to Gardiner Project

We've now built fiber to more than 650 homes and connected over 100 homes and business to our new publicly owned, super high-speed network. We've come a long way, but with over 1200 total locations signed up for fiber in the project area, we've still got a ways to go.

If you are one of the 650 homes with fiber to an outside wall but no service, skip to the updated table below for in home installation timelines. Oh, also, expect to see our splicing contractors come by to install a box to the outside of your home in the coming weeks and months (pictured right).

If you are one of the 600 homes who haven't seen construction, be on the lookout for a phone call from our contractor soon. They are working to design the best route from the street to your house. Input from you helps ensure they can avoid any obstacles and get the fiber to the home at the best spot for you and the PUD. They're moving fast and will need to estimate the best route if they can't get a hold of you. 

When Will I Get Internet? 

The answer varies depending on where you live, or in which PON.  There are two large groupings of PONs: Quilcene and Gardiner. Within each grouping are the sub-PONs labeled A-H. PON locations are pictured in the maps below. Estimated install dates are listed in the following table. Note, we continue to experience splicing delays and have had to push back installs one more month since the last update. However, we expect to make up time in September and should be back on course after the delay. 

Area         Drop StatusIn-Home Install Schedule
QUIL PON B      95%90% Complete
QUIL PON D
75%October
QUIL PON G
75%October
QUIL PON H
60%October
QUIL PON C
75%October
QUIL PON F
60%November
QUIL PON E
80%
November
QUIL PON A     50%             November                        
Area Drop Status
In-Home Install Schedule
GARD PON E        75% Complete
December
GARD PON F
40%December
GARD PON G
50%January
GARD PON D
30%January
GARD PON C
not started
February
GARD PON B
not started
February
GARD PON A
not started

March


Past the Threshold

As of the end of August, we've passed the 60% threshold for registrations in the entire project area. This means that we have both met and exceeded our goals! But it also means any new signups will have to pay $750 for installation. Which might sound like a lot, but as this fiber build-out is a once-in-a-generation opportunity, we highly encourage residents to take part. After the construction project is completed, costs to install fiber will be in the $3000-$10,000 range. Also, the $750 charge can be paid over 36 months with a $100 deposit if anyone needs to spread the payments out. If any of your neighbors haven't yet registered for fiber, there's still time. They can do so on our website.

Monthly Service Options

If you haven't already, please make sure to review our monthly service offeringsMonthly internet service is available from the PUD directly, or through one of our Qualified Internet Service Providers

Fiber Kickoff at the Quilcene Fair

Be sure to join us at the Quilcene Fair from 11-3pm on Saturday, September 21st for our fiber project kickoff event. We'll have our fiber trucks in the parade, our staff and commissioners will host a demonstration booth and we'll have a ribbon cutting at noon. Come by to be in the group photo. We'll also be giving tours of some of the completed project sites.


View more updates